REPAIR OF AIR TRANSITIONS FROM THE SYSTEM OF “BULGARGAZ” EAD

OBJECT:
"Ongoing repair of air transitions from the gas transmission system of 'Bulgargaz' EAD "
Client
“BULGARGAZ“ EAD
Contractor:
“VECTOR CONSTRUCT“ Ltd
Location:
Pazardzhik – Ihtiman

Description:

The project involves the rehabilitation of 23 air transitions from the main gas pipeline (Φ 711) to Greece and the transit gas pipeline (Φ 1020) to North Macedonia. The repair of the facilities is necessary due to the compromise of the anticorrosive coating on the pipes as a result of the lack of protective insulation tape at the transitions from ground to air. At both ends of the transitions, there are no barriers with warning signs, which creates conditions for unauthorized access to the gas pipelines, posing risks of incidents or damage to the infrastructure.

Details

The repair works were carried out in extremely difficult access conditions, with the facilities located in mountainous areas;
The restoration of the anticorrosive coating on the pipelines was performed by climbers using the rope access method;
The pipes were cleaned of rust and dirt, primed, and painted twice with silver Ferolite;
The protective insulation tape was replaced at both ends of the transitions, and barriers with warning signs were installed.