RAILWAY BRIDGE REPAIR – RUSE

OBJECT:
“Restoration of the anti-corrosion coating of a steel bridge at km 12+849 in the section between Ruse – Dolapite (2,460 m²) on the 4th railway line”
Client
“NATIONAL RAILWAY INFRASTRUCTURE“ COMPANY
Contractor:
“VECTOR KONSTRUCT” Ltd
Location:
Ruse

Description:

The project was carried out following a general inspection of bridge structures within the National Railway Infrastructure Company’s network. The inspection revealed significant deterioration of the anti-corrosion coating on the bridge, which is part of the 4th railway line connecting Bulgaria and Romania. To preserve the steel structure, the entire surface was cleaned by sandblasting, then primed and coated twice with alkyd paint. The works were executed without interrupting railway traffic, except for the parapets on both sides of the bridge, which were repaired during designated “electrical train windows.”

Details

A special suspended platform was built to ensure access to all parts of the bridge;
High and hard-to-reach areas were handled by technicians certified for rope-access work;
Metal surfaces were sandblasted to a metallic shine (SA 3 standard);
The total treated metal surface area amounts to 2,460 m².